Contract question · Force majeure and hardship
Hardship and change of circumstances: section 313 BGB and contract clauses
Short answer
German law allows adaptation where circumstances forming the basis of the contract have changed seriously after signature and holding a party to the contract is unreasonable (§ 313(1) BGB); the contractual allocation of risk takes priority.
English law has no general doctrine of hardship; a fixed-price contract stays fixed unless the contract provides for adjustment or the contract is frustrated. A hardship clause, such as the ICC Hardship Clause 2020, fills the gap.
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| German law | adaptation; termination as last resort | § 313(1), (3) BGB |
| English law | no hardship doctrine; frustration only | case law |
| Contract solution | renegotiation duty, then adaptation or termination | ICC Hardship Clause 2020 |
Counter-proposal
Typical demand of the other side
The contractor waives all claims for change of circumstances.
Counter-proposal, generic example (not taken from customer contracts)
If, after signature, circumstances beyond the parties' control change so that performance becomes excessively onerous for one party, the parties shall negotiate an adjustment within 30 days. Failing agreement, § 313 BGB applies.
Related questions
- Can § 313 BGB be excluded in standard terms?
- A complete exclusion conflicts with the core of the provision and is open to challenge under § 307 BGB.
- How does hardship differ from force majeure?
- Force majeure concerns the ability to perform; hardship concerns the balance of the contract.
- Did the 2022 energy price rise trigger § 313 BGB?
- German courts decided case by case; foreseeability, magnitude and the contractual risk allocation were decisive.
Sources
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).