Contract question · Force majeure and hardship
Force majeure clause: definition, notice, consequences
Short answer
Neither English nor German law defines force majeure; without a clause, English law offers only frustration and German law impossibility (§ 275 BGB), absence of fault in delay (§ 286(4) BGB) and hardship (§ 313 BGB).
FIDIC 2017 uses "Exceptional Events" (Clause 18) with notice within 14 days; the ICC Force Majeure Clause 2020 is a common starting point for supply contracts.
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| English law without clause | frustration only | Taylor v Caldwell (1863) |
| German law without clause | impossibility; no damages without fault | § 275, § 286(4) BGB |
| FIDIC 2017 | Exceptional Events, notice within 14 days | Clause 18 |
| CISG | exemption from damages for impediment beyond control | Art. 79 CISG |
| Model | ICC Force Majeure Clause 2020 | ICC |
Counter-proposal
Typical demand of the other side
Force majeure relieves only the employer; supply shortages, strikes and epidemics are not force majeure for the contractor.
Counter-proposal, generic example (not taken from customer contracts)
Force majeure means an event beyond the control of the affected party, not foreseeable at signature, whose effects cannot be avoided by reasonable means, including war, terrorism, natural disasters, epidemics, government action, embargoes and industrial action outside the affected party's own workforce. The affected party gives notice within 14 days. Time for performance is extended by the duration of the impediment; if it lasts more than 120 days, either party may terminate. The clause applies to both parties.
Related questions
- Is a strike force majeure?
- Only if the clause says so; strikes within the own workforce are often excluded, industry-wide strikes often included.
- Is notice a condition precedent?
- That depends on the wording; under English law clear wording is needed to make notice a condition precedent to relief.
- Does force majeure cover price increases?
- No; it addresses inability to perform. Cost increases belong in a price adjustment or hardship clause.
Sources
- ICC Force Majeure and Hardship Clauses 2020
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- United Nations Convention on Contracts for the International Sale of Goods (CISG)
- German Civil Code (BGB), English translation
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).