Liquidated damages for delay: buyer demands
Rate per week of delay and cap on delay damages in 6 published sales conditions.
Range
| Metric | Range | Sets of terms |
|---|---|---|
| Rate per week of delay | 0.5% to 1% per week | 5 sets of terms (supplier side) |
| Cap on delay damages | 5% to 10% | 6 sets of terms (supplier side) |
Buyer side: fewer than three sets of terms with quantified values; individual values after sign-in.
Basis: total or contract price; in 3 sales conditions the value of the delayed or unusable part of the delivery. The same percentage therefore yields different amounts.
Supplier position
Rate per week of delay: most frequent value 0.5% (4 of 5 sales conditions), range in sales conditions 0.5% to 1%.
Cap: most frequent value 5% (4 of 6 sales conditions), range in sales conditions 5% to 10%.
Elements of sales conditions besides rate and cap
- Grace period before the first payment
- Liquidated damages as the sole remedy for delay
- Time bar for written notice of the claim
- Calculation on the value of the unusable part instead of the contract price
Further demands in purchase conditions
- Payable without prior notice, with set-off at the buyer's discretion
- Liquidated damages for performance values such as noise, weight and reliability in addition to delay damages, with a separate cap
- Designation as a contractual penalty instead of liquidated damages, with consequences for judicial reduction depending on the legal system
Review of your own contract
Finding per clause
Rate, cap, basis and due date of the liquidated damages in your own contract against the benchmark of the seller register, with quotation and clause reference.
Rating and counter-proposal
Rating per finding and counter-proposal in the language of the contract, ready for the deviation list.
Amount per clause
With a contract value on record, the amount of liquidated damages up to the cap; without a contract value, the rule without a euro amount.
Missing clause
A missing cap or a missing sole-remedy limitation is reported as a separate finding.
Individual values with reference
Individual value, set of terms, version and clause reference are in CLEVER after sign-in, in the search under "Market reference T&Cs".
Data basis
Evaluation of published terms and conditions with a publicly available source only: purchase conditions 4, sales conditions 9. One value per set of terms and metric.
Purchase conditions read in full (as of 2026-08-28); sales conditions from search extracts (as of 2026-10-15). Range recalculated on every change to the data basis.
Inclusion of a topic from 3 sets of terms with quantified values; inclusion of the buyer or supplier side in the range from 3 sets of terms with quantified values per side.