FIDIC Red, Yellow and Silver Book: allocation of risk compared
Short answer
The Red Book (Construction) assumes design by the employer, the Yellow Book (Plant and Design-Build) puts design with the contractor, and the Silver Book (EPC/Turnkey) additionally transfers most of the risk of unforeseeable conditions to the contractor.
In the Red and Yellow Books an Engineer administers the contract; in the Silver Book the employer acts itself. The 2017 edition treats claims of both parties in Clause 20.
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Red Book | employer design; measured unit rates | FIDIC 2017 |
| Yellow Book | contractor design; lump sum | FIDIC 2017 |
| Silver Book | EPC turnkey; unforeseeable risk largely with contractor | FIDIC 2017 |
| Contract administration | Engineer (Red, Yellow); Employer (Silver) | FIDIC 2017 |
| Notice of claim | 28 days after awareness | Sub-Clause 20.2.1 |
Counter-proposal
Typical demand of the other side
Silver Book with the contractor assuming ground risk and the accuracy of tender data, with a four-week bid period.
Counter-proposal, generic example (not taken from customer contracts)
Yellow Book with Particular Conditions: unforeseeable physical conditions with the employer under Sub-Clause 4.12, employer responsible for the accuracy of data it provides, liability cap under Sub-Clause 1.15 at the Accepted Contract Amount.
Related questions
- Which book suits a plant with supplier design?
- The Yellow Book; the Silver Book is designed for projects where the employer trades price and time certainty for greater risk transfer.
- Where are the project-specific values?
- In the Contract Data and Particular Conditions, including delay damages, maximum amount and performance security.
- Are there other FIDIC books?
- Yes, among others the Green Book (short form), the White Book (consultancy) and the Gold Book (design, build and operate).
Sources
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).