Contract question · FIDIC and VOB/B
Notice of claim under FIDIC 2017: the 28-day time bar
Short answer
Under FIDIC 2017 a claim for extension of time or additional payment must be notified within 28 days after the claimant became aware of the event (Sub-Clause 20.2.1); otherwise the claim is lost.
A fully detailed claim follows within 84 days (Sub-Clause 20.2.4). Under German law a time bar in standard terms is subject to control under § 307 BGB; English courts enforce clear time bars.
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Notice of Claim | 28 days after awareness | Sub-Clause 20.2.1 |
| Fully detailed Claim | 84 days after awareness | Sub-Clause 20.2.4 |
| Consequence of late notice | claim lost (time bar) | Sub-Clause 20.2.1 |
| German standard terms | reasonableness control | § 307 BGB |
Counter-proposal
Typical demand of the other side
Contractor claims must be notified within 7 days and substantiated within 14 days; otherwise they are barred.
Counter-proposal, generic example (not taken from customer contracts)
The time limits of Sub-Clause 20.2 of the FIDIC 2017 conditions apply. Time limits in subcontracts are set 7 days shorter so that the main contractor can give notice in time.
Related questions
- Does the time bar apply to the employer?
- In the 2017 edition yes: Clause 20 covers claims of both parties.
- Can late notice be excused?
- Under Sub-Clause 20.2.5 circumstances justifying late submission may be taken into account in the determination of the claim.
- Are time bars enforceable under English law?
- English courts enforce time bars that are clearly drafted.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- German Civil Code (BGB), English translation
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).