Notice of claim under FIDIC 2017: the 28-day time bar

Short answer

Under FIDIC 2017 a claim for extension of time or additional payment must be notified within 28 days after the claimant became aware of the event (Sub-Clause 20.2.1); otherwise the claim is lost.

A fully detailed claim follows within 84 days (Sub-Clause 20.2.4). Under German law a time bar in standard terms is subject to control under § 307 BGB; English courts enforce clear time bars.

Range and benchmark

MetricValueBasis
Notice of Claim28 days after awarenessSub-Clause 20.2.1
Fully detailed Claim84 days after awarenessSub-Clause 20.2.4
Consequence of late noticeclaim lost (time bar)Sub-Clause 20.2.1
German standard termsreasonableness control§ 307 BGB

Counter-proposal

Typical demand of the other side

Contractor claims must be notified within 7 days and substantiated within 14 days; otherwise they are barred.

Counter-proposal, generic example (not taken from customer contracts)

The time limits of Sub-Clause 20.2 of the FIDIC 2017 conditions apply. Time limits in subcontracts are set 7 days shorter so that the main contractor can give notice in time.

Related questions

Does the time bar apply to the employer?
In the 2017 edition yes: Clause 20 covers claims of both parties.
Can late notice be excused?
Under Sub-Clause 20.2.5 circumstances justifying late submission may be taken into account in the determination of the claim.
Are time bars enforceable under English law?
English courts enforce time bars that are clearly drafted.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).