Contract question · Defects and warranty

Defects liability period: FIDIC, German law, English limitation

Short answer

FIDIC 2017 uses a Defects Notification Period stated in the Contract Data; if none is stated, it is one year from the date of completion in the Taking-Over Certificate (Sub-Clauses 1.1 and 11).

Under German law defect claims become time-barred after two years, five years for buildings (§ 438, § 634a BGB); under VOB/B four years for buildings and two years for maintenance-relevant parts of machinery where maintenance is not entrusted to the contractor (§ 13(4) VOB/B). Under English law a simple contract claim is barred after six years, a deed after twelve (Limitation Act 1980 s. 5 and s. 8).

Range and benchmark

MetricValueBasis
FIDIC 2017 default1 year (Defects Notification Period)Sub-Clause 1.1, Clause 11
Germany, sale or works2 years§ 438(1) No. 3, § 634a(1) No. 1 BGB
Germany, buildings5 years; 4 years under VOB/B§ 634a(1) No. 2 BGB; § 13(4) VOB/B
England, simple contract / deed6 years / 12 yearsLimitation Act 1980 s. 5, s. 8

Counter-proposal

Typical demand of the other side

Defects liability period of 60 months from taking-over of the complete plant, restarting for each repaired part.

Counter-proposal, generic example (not taken from customer contracts)

Defects Notification Period of 24 months from taking-over, at the latest 30 months from readiness for delivery. Repaired or replaced parts have a new period of 12 months, not extending beyond 36 months from taking-over.

Related questions

Is the defects period the same as the limitation period?
No. The defects period is the window to notify and remedy defects; the limitation period governs when a claim can no longer be enforced. FIDIC and English law keep the two apart.
Does the period restart after repair?
Under FIDIC 2017 Sub-Clause 11.3 the Employer may extend the period for a part that cannot be used due to a defect, up to a total of two years beyond the original period unless stated otherwise.
When does the period start?
Under German law with delivery or acceptance (§ 438(2), § 634a(2) BGB); under FIDIC with the completion date stated in the Taking-Over Certificate.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).