Contract question · Defects and warranty
Defects liability period: FIDIC, German law, English limitation
Short answer
FIDIC 2017 uses a Defects Notification Period stated in the Contract Data; if none is stated, it is one year from the date of completion in the Taking-Over Certificate (Sub-Clauses 1.1 and 11).
Under German law defect claims become time-barred after two years, five years for buildings (§ 438, § 634a BGB); under VOB/B four years for buildings and two years for maintenance-relevant parts of machinery where maintenance is not entrusted to the contractor (§ 13(4) VOB/B). Under English law a simple contract claim is barred after six years, a deed after twelve (Limitation Act 1980 s. 5 and s. 8).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| FIDIC 2017 default | 1 year (Defects Notification Period) | Sub-Clause 1.1, Clause 11 |
| Germany, sale or works | 2 years | § 438(1) No. 3, § 634a(1) No. 1 BGB |
| Germany, buildings | 5 years; 4 years under VOB/B | § 634a(1) No. 2 BGB; § 13(4) VOB/B |
| England, simple contract / deed | 6 years / 12 years | Limitation Act 1980 s. 5, s. 8 |
Counter-proposal
Typical demand of the other side
Defects liability period of 60 months from taking-over of the complete plant, restarting for each repaired part.
Counter-proposal, generic example (not taken from customer contracts)
Defects Notification Period of 24 months from taking-over, at the latest 30 months from readiness for delivery. Repaired or replaced parts have a new period of 12 months, not extending beyond 36 months from taking-over.
Related questions
- Is the defects period the same as the limitation period?
- No. The defects period is the window to notify and remedy defects; the limitation period governs when a claim can no longer be enforced. FIDIC and English law keep the two apart.
- Does the period restart after repair?
- Under FIDIC 2017 Sub-Clause 11.3 the Employer may extend the period for a part that cannot be used due to a defect, up to a total of two years beyond the original period unless stated otherwise.
- When does the period start?
- Under German law with delivery or acceptance (§ 438(2), § 634a(2) BGB); under FIDIC with the completion date stated in the Taking-Over Certificate.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- German Civil Code (BGB), English translation
- § 13 VOB/B (German)
- Limitation Act 1980 (UK)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract