Contract question · Defects and warranty
Notice of defects under section 377 German Commercial Code
Short answer
In a sale that is commercial for both parties, the buyer must inspect the goods without undue delay after delivery and give notice of a defect without undue delay; otherwise the goods are deemed approved (§ 377(1) and (2) HGB).
Under the CISG the buyer must give notice within a reasonable time and at the latest within two years (Art. 39 CISG).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Inspection | without undue delay after delivery | § 377(1) HGB |
| Late notice | goods deemed approved | § 377(2) HGB |
| Hidden defect | notice without undue delay after discovery | § 377(3) HGB |
| CISG | reasonable time, at most 2 years | Art. 39 CISG |
Counter-proposal
Typical demand of the other side
The buyer is released from the duty to inspect and notify under § 377 HGB; defects may be notified throughout the warranty period.
Counter-proposal, generic example (not taken from customer contracts)
Obvious defects shall be notified in writing within 10 working days after delivery, hidden defects within 10 working days after discovery. Otherwise § 377 HGB applies.
Related questions
- Does § 377 HGB apply to works contracts?
- Not to pure works contracts with acceptance; it applies to contracts for the supply of movable goods to be manufactured (§ 650 BGB).
- Is "without undue delay" a fixed number of days?
- No; courts assess it by the type of goods and the business, often within a few working days for obvious defects.
- Can buyer's terms exclude § 377 HGB?
- A complete exclusion in the buyer's standard terms is widely considered unreasonable; extending the notice period is common.
Sources
- German Commercial Code (HGB), English translation
- United Nations Convention on Contracts for the International Sale of Goods (CISG)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).