Contract question · Liquidated damages
Liquidated damages in plant engineering: usual rate and cap
Short answer
Published sales conditions for machinery and plant set delay damages at 0.5% to 1% per week of delay, capped at 5% to 10% of the reference value.
Under FIDIC 2017, the daily rate and the maximum amount of Delay Damages are stated in the Contract Data (Sub-Clause 8.8).
Under German law, a cap above 5 % of the contract sum in standard construction terms is invalid (BGH, 23 January 2003, VII ZR 210/01).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Rate per week of delay | 0.5% to 1% | 5 published sales conditions (CLEVER market reference) |
| Cap | 5% to 10% | 6 published sales conditions (CLEVER market reference) |
| Supplier-side benchmark | 0.5% per commenced week, cap 10% of the contract price | CLEVER supplier-side register, practice value |
| FIDIC 2017 | rate and maximum in the Contract Data | Sub-Clause 8.8 |
| German standard terms, construction | cap at most 5% of the contract sum | BGH VII ZR 210/01 |
Counter-proposal
Typical demand of the other side
1% of the total contract value per commenced week of delay, up to 15%, without prejudice to further damages.
Counter-proposal, generic example (not taken from customer contracts)
Delay damages of 0.5% of the price of the delayed part of the supply per completed week, not exceeding 5% of that price. Delay damages are the sole remedy for delay, except in case of wilful misconduct or gross negligence.
Related questions
- Are liquidated damages the sole remedy for delay?
- Only if the contract says so. Under German law a contractual penalty is a minimum amount of damages (§ 340(2) BGB); a sole-remedy clause excludes further claims for delay.
- Can a court reduce excessive liquidated damages?
- Under German law a court may reduce a disproportionate penalty (§ 343 BGB), but not one promised by a merchant in the course of business (§ 348 HGB). Under English law an extravagant clause is unenforceable as a penalty (Makdessi).
- What is the difference between a delay cap and a liability cap?
- The delay cap limits delay damages; the liability cap limits total liability. Supplier-side drafting counts delay damages towards the liability cap.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- German Civil Code (BGB), English translation
- German Commercial Code (HGB), English translation
- Federal Court of Justice (BGH), judgment of 23.01.2003, VII ZR 210/01
- Cavendish Square Holding BV v Makdessi [2015] UKSC 67
- CLEVER supplier-side register, market anchors (practice values, as of 8 October 2026)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).