Contract question · Liquidated damages

Liquidated damages in plant engineering: usual rate and cap

Short answer

Published sales conditions for machinery and plant set delay damages at 0.5% to 1% per week of delay, capped at 5% to 10% of the reference value.

Under FIDIC 2017, the daily rate and the maximum amount of Delay Damages are stated in the Contract Data (Sub-Clause 8.8).

Under German law, a cap above 5 % of the contract sum in standard construction terms is invalid (BGH, 23 January 2003, VII ZR 210/01).

Range and benchmark

MetricValueBasis
Rate per week of delay0.5% to 1%5 published sales conditions (CLEVER market reference)
Cap5% to 10%6 published sales conditions (CLEVER market reference)
Supplier-side benchmark0.5% per commenced week, cap 10% of the contract priceCLEVER supplier-side register, practice value
FIDIC 2017rate and maximum in the Contract DataSub-Clause 8.8
German standard terms, constructioncap at most 5% of the contract sumBGH VII ZR 210/01

Counter-proposal

Typical demand of the other side

1% of the total contract value per commenced week of delay, up to 15%, without prejudice to further damages.

Counter-proposal, generic example (not taken from customer contracts)

Delay damages of 0.5% of the price of the delayed part of the supply per completed week, not exceeding 5% of that price. Delay damages are the sole remedy for delay, except in case of wilful misconduct or gross negligence.

Related questions

Are liquidated damages the sole remedy for delay?
Only if the contract says so. Under German law a contractual penalty is a minimum amount of damages (§ 340(2) BGB); a sole-remedy clause excludes further claims for delay.
Can a court reduce excessive liquidated damages?
Under German law a court may reduce a disproportionate penalty (§ 343 BGB), but not one promised by a merchant in the course of business (§ 348 HGB). Under English law an extravagant clause is unenforceable as a penalty (Makdessi).
What is the difference between a delay cap and a liability cap?
The delay cap limits delay damages; the liability cap limits total liability. Supplier-side drafting counts delay damages towards the liability cap.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).