Contract question · Limitation of liability
Limitation of liability in plant contracts: cap as a share of contract value
Short answer
Published sales conditions cap total liability at 10% to 100% of the contract price.
The CLEVER supplier-side benchmark depends on complexity: 100% of contract value for a simple scope, 25% to 40% for system integration with intervention in existing plant.
FIDIC 2017 caps total liability at the sum in the Contract Data or, if none is stated, the Accepted Contract Amount; the cap does not apply to fraud, gross negligence, deliberate default or reckless misconduct (Sub-Clause 1.15).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Cap in sales conditions | 10% to 100% of the contract price | 4 published sales conditions (CLEVER market reference) |
| Benchmark, simple scope | 100% of contract value | CLEVER supplier-side register, practice value |
| Benchmark, complex system integration | 25% to 40% of contract value | CLEVER supplier-side register, practice value |
| FIDIC 2017 default | Accepted Contract Amount | Sub-Clause 1.15 |
| Not limitable, England | death or personal injury from negligence | UCTA 1977 s. 2(1) |
| Not limitable, Germany | intent; in standard terms also gross negligence and personal injury | § 276(3), § 309 No. 7 BGB |
Counter-proposal
Typical demand of the other side
The contractor's liability is unlimited.
Counter-proposal, generic example (not taken from customer contracts)
The contractor's total aggregate liability arising out of or in connection with this contract shall not exceed 40% of the contract price; delay damages count towards this cap. The cap does not apply to wilful misconduct, gross negligence, death or personal injury, or liability under mandatory product liability law.
Related questions
- Is the cap per claim or in aggregate?
- The wording decides. "Per event" and "in aggregate over the term" produce different exposure; the aggregate cap is the narrower one.
- Does a cap need to pass a reasonableness test in England?
- Where one party deals on the other's written standard terms, a limitation is subject to the reasonableness test under UCTA 1977 s. 3 and s. 11.
- Should indemnities sit inside the cap?
- Supplier-side drafting brings indemnities inside the cap except for third-party personal injury and IP infringement; buyer-side drafting keeps them outside.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- Unfair Contract Terms Act 1977 (UK)
- German Civil Code (BGB), English translation
- CLEVER supplier-side register, market anchors (practice values, as of 8 October 2026)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract