Taking-over and acceptance of plant: tests, certificate, deemed taking-over

Short answer

Under FIDIC 2017 the works are taken over when they have passed the Tests on Completion and a Taking-Over Certificate has been issued or is deemed issued (Clauses 9 and 10).

Under German law acceptance (§ 640 BGB) makes the price due (§ 641 BGB), passes the risk (§ 644 BGB) and starts the limitation period (§ 634a(2) BGB); acceptance may not be refused for insignificant defects.

Range and benchmark

MetricValueBasis
FIDIC prerequisiteTests on Completion passedClause 9
FIDIC certificateTaking-Over Certificate, or deemed issuedSub-Clause 10.1
German acceptance: effectsprice due, risk passes, limitation starts§§ 641, 644, 634a BGB
Refusal for minor defectsnot permitted§ 640(1) BGB

Counter-proposal

Typical demand of the other side

Acceptance follows 90 days of fault-free trial operation; the employer decides on acceptance at its discretion.

Counter-proposal, generic example (not taken from customer contracts)

Acceptance follows a 72-hour trial run in which the guaranteed values in Annex X are reached within the stated tolerances. If the trial run is delayed for more than 30 days for reasons not attributable to the contractor, the plant is deemed accepted. Minor defects do not prevent acceptance; they are recorded in a punch list with deadlines.

Related questions

What is the difference between commissioning and taking-over?
Commissioning is a technical process; taking-over or acceptance is the legal step with defined consequences for payment, risk and defects periods.
Can acceptance be at the employer's discretion?
Not under German standard terms: § 640(1) BGB obliges the employer to accept work that conforms to the contract.
Are partial taking-overs possible?
FIDIC provides for taking-over of parts (Sub-Clause 10.2); VOB/B provides partial acceptance of self-contained parts on request (§ 12(2) VOB/B).

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).