Performance bond and performance security: usual amount and term

Short answer

FIDIC 2017 requires the contractor to provide a Performance Security in the amount and currency stated in the Contract Data (Sub-Clause 4.2).

The CLEVER supplier-side benchmark is 5% to 10% of contract value; German public employers should not require more than 5% of the contract sum for performance (§ 9c(2) VOB/A). Buyer-side terms open with 15% on first demand.

Range and benchmark

MetricValueBasis
FIDIC 2017amount in Contract DataSub-Clause 4.2
Supplier-side benchmark5% to 10% of contract valueCLEVER supplier-side register
German public employersat most 5% of the contract sum§ 9c(2) VOB/A
Buyer opening position15% on first demand, irrevocableCLEVER supplier-side register, published purchase conditions

Counter-proposal

Typical demand of the other side

Unlimited performance guarantee on first demand for 15% of the contract sum.

Counter-proposal, generic example (not taken from customer contracts)

Performance security by a bank or credit insurer for 5% of the net contract price, valid until taking-over plus 60 days, to be returned against the defects security.

Related questions

What is the difference between a performance bond and a bank guarantee?
A conditional (surety) bond requires proof of the contractor's default; an on-demand guarantee pays against a compliant demand. Bank guarantees in international projects are usually on demand under URDG 758.
How much does a performance bond cost?
An annual fee of the issuing bank or insurer as a percentage of the bond amount, depending on credit rating.
When must the security be returned?
Under VOB/B after acceptance once the defects security is provided (§ 17(8) No. 1 VOB/B); under FIDIC 2017 the return is governed by Sub-Clause 4.2 and the contract.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).