On-demand guarantee under German law

Short answer

A clause in the employer's standard terms requiring a performance guarantee payable on first demand is invalid under German law (BGH, 18 April 2002, VII ZR 192/01; for public employers BGH, 25 March 2004, VII ZR 453/02).

VOB/B excludes guarantees on first demand as security (§ 17(4) VOB/B). In international projects under other laws, demand guarantees under URDG 758 are standard.

Range and benchmark

MetricValueBasis
German standard termson-demand performance guarantee invalidBGH VII ZR 192/01
VOB/Bon-demand guarantee cannot be required§ 17(4) VOB/B
Individually negotiatedpermitted§ 305(1) BGB
International practiceURDG 758 demand guaranteesICC

Counter-proposal

Typical demand of the other side

Irrevocable guarantee on first demand, waiving all defences.

Counter-proposal, generic example (not taken from customer contracts)

Unlimited, directly enforceable (selbstschuldnerische) guarantee by an EU-licensed bank or credit insurer, waiving the defence of prior enforcement against the principal debtor.

Related questions

What replaces an invalid clause?
The court interprets the contract as requiring an unlimited, directly enforceable guarantee without the on-demand feature (BGH VII ZR 192/01).
Does the rule apply to advance payment guarantees?
An advance payment guarantee secures repayment of money already paid; courts treat it differently from performance security.
Does it apply under English law?
No. The German rule applies where German law governs the security agreement.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).