Contract question · Price adjustment
Price escalation clause: formula, index, threshold
Short answer
A price escalation clause splits the price into a fixed share and adjustable shares for labour and materials, adjusted by published indices: P = P0 × (a + b × L/L0 + c × M/M0), with a + b + c = 1.
FIDIC 2017 provides adjustment for changes in cost through a Schedule of cost indexation (Sub-Clause 13.7). Under German law a cost-element clause is permitted (§ 1(2) No. 3 Price Clauses Act), while indexation to a general price index is generally prohibited (§ 1(1)).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Formula | P = P0 × (a + b × L/L0 + c × M/M0) | contract practice |
| FIDIC 2017 | Schedule of cost indexation | Sub-Clause 13.7 |
| German law, cost-element clause | permitted | § 1(2) No. 3 PrKG |
| German law, general index | generally prohibited | § 1(1) PrKG |
Counter-proposal
Typical demand of the other side
Prices are fixed until final acceptance.
Counter-proposal, generic example (not taken from customer contracts)
20% of the price is fixed; 40% is adjusted by the producer price index for steel and 40% by the index of negotiated wages in mechanical engineering, comparing the month of the offer with the month of delivery. Adjustment applies where the total price changes by more than 2%, works in both directions and is capped at 15% of the contract price.
Related questions
- Which indices are suitable?
- Official indices with a link to the cost structure, published by a statistics office and not influenced by either party.
- Should the clause work in both directions?
- A clause that only allows increases is open to challenge in German standard terms; two-way adjustment is the usual design.
- Is a threshold common?
- Yes; a threshold avoids small adjustments and a cap limits the exposure of the buyer.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- German Price Clauses Act (PrKG), § 1
- Federal Statistical Office (Destatis), GENESIS-Online
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).