Extension of time and notice of delay

Short answer

Under FIDIC 2017 the contractor is entitled to an Extension of Time for listed causes, including variations, exceptional adverse climatic conditions and delay caused by the employer, subject to a notice of claim within 28 days (Sub-Clauses 8.5 and 20.2).

Under German VOB/B the contractor must give written notice of a hindrance without undue delay; time periods are extended by the duration of the hindrance plus an allowance for resumption (§ 6(1), (2) and (4) VOB/B).

Range and benchmark

MetricValueBasis
FIDIC entitlementExtension of Time for listed causesSub-Clause 8.5
FIDIC notice28 days after awarenessSub-Clause 20.2.1
VOB/B noticewritten, without undue delay§ 6(1) VOB/B
VOB/B extensionduration of hindrance plus resumption allowance§ 6(4) VOB/B

Counter-proposal

Typical demand of the other side

Extensions of time require the written approval of the employer; hindrances must be notified within 24 hours.

Counter-proposal, generic example (not taken from customer contracts)

The contractor shall notify hindrances without undue delay, at the latest within 7 calendar days of becoming aware, in writing. Time for completion is extended by the duration of the hindrance plus a reasonable allowance for resumption; the extended time replaces the agreed time also for delay damages.

Related questions

What happens to delay damages if the employer causes delay?
Under English law the prevention principle prevents the employer from levying delay damages for delay it caused, unless the contract provides an extension mechanism (Multiplex v Honeywell [2007] EWHC 447 (TCC)).
What should a notice of delay contain?
The event, its start, the affected work and the expected effect on the programme.
Does the employer need to approve the notice?
No. The notice informs; entitlement depends on whether the cause and its effect are established.

Sources

As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.

Further pages

Other languages: FrançaisEspañolPortuguêsالعربيةहिन्दी

Review of your own contract

CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.

Book a demoStart a trial3 contract reviews free, no credit card

Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).