Contract question · Delay and extension of time
Extension of time and notice of delay
Short answer
Under FIDIC 2017 the contractor is entitled to an Extension of Time for listed causes, including variations, exceptional adverse climatic conditions and delay caused by the employer, subject to a notice of claim within 28 days (Sub-Clauses 8.5 and 20.2).
Under German VOB/B the contractor must give written notice of a hindrance without undue delay; time periods are extended by the duration of the hindrance plus an allowance for resumption (§ 6(1), (2) and (4) VOB/B).
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| FIDIC entitlement | Extension of Time for listed causes | Sub-Clause 8.5 |
| FIDIC notice | 28 days after awareness | Sub-Clause 20.2.1 |
| VOB/B notice | written, without undue delay | § 6(1) VOB/B |
| VOB/B extension | duration of hindrance plus resumption allowance | § 6(4) VOB/B |
Counter-proposal
Typical demand of the other side
Extensions of time require the written approval of the employer; hindrances must be notified within 24 hours.
Counter-proposal, generic example (not taken from customer contracts)
The contractor shall notify hindrances without undue delay, at the latest within 7 calendar days of becoming aware, in writing. Time for completion is extended by the duration of the hindrance plus a reasonable allowance for resumption; the extended time replaces the agreed time also for delay damages.
Related questions
- What happens to delay damages if the employer causes delay?
- Under English law the prevention principle prevents the employer from levying delay damages for delay it caused, unless the contract provides an extension mechanism (Multiplex v Honeywell [2007] EWHC 447 (TCC)).
- What should a notice of delay contain?
- The event, its start, the affected work and the expected effect on the programme.
- Does the employer need to approve the notice?
- No. The notice informs; entitlement depends on whether the cause and its effect are established.
Sources
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
- § 6 VOB/B (German)
- Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd [2007] EWHC 447 (TCC)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract