Contract question · Subcontracts and flow-down
Back-to-back subcontract: obligations to flow down
Short answer
The main contractor is liable to the employer for its subcontractor as for its own fault (§ 278 BGB); whatever it does not flow down, it carries itself.
Back-to-back means: programme, scope, taking-over procedure, defects periods, notice periods and liability rules of the subcontract match the main contract, with shorter notice periods in the subcontract so that the main contractor can meet its own deadlines.
Range and benchmark
| Metric | Value | Basis |
|---|---|---|
| Liability for subcontractors, Germany | as for own fault | § 278 BGB |
| Defects period | link to taking-over under the main contract | contract practice |
| Notice of claim | shorter than under the main contract | FIDIC 2017 Sub-Clause 20.2; contract practice |
| Main contract terms | relevant parts attached to the subcontract | contract practice |
Counter-proposal
Typical demand of the other side
The subcontractor assumes all obligations of the main contractor under the main contract insofar as they concern its scope; the main contract is not disclosed.
Counter-proposal, generic example (not taken from customer contracts)
The provisions of the main contract reproduced in Annex X apply to the subcontractor's scope. Provisions not disclosed to the subcontractor do not apply. Delay damages and liability of the subcontractor relate pro rata to the value of its scope.
Related questions
- Is a blanket reference to the main contract effective?
- Under German standard terms only if the subcontractor could reasonably take note of the content (§ 305(2) BGB).
- Who checks consistency between main contract and subcontract?
- Usually project procurement; CLEVER compares main contract and subcontract clause by clause and shows gaps per topic.
- Does FIDIC provide a subcontract form?
- FIDIC publishes conditions of subcontract designed to match its main contract forms.
Sources
- German Civil Code (BGB), English translation
- FIDIC Conditions of Contract, 2017 edition (Red, Yellow, Silver Book)
As of 17 November 2026. Statutory texts retrieved on 17 November 2026; case law with date and reference.
Further pages
Review of your own contract
CLEVER reviews your contract clause by clause against the supplier-side register and gives, for each finding, the location, the rating and a counter-proposal in the contract language.
Not legal advice. CLEVER produces draft wording for internal review; your own legal or contract team decides. No legal services within the meaning of the German Legal Services Act (RDG).